Lakewood approves the first
116 homes at The Parke
By Justin Kelly
NJ Real Estate Broker-Salesperson
Lakewood's planning board approved the first phase of The Parke at Lakewood on September 1. The plan creates 129 lots off Cross Street, and the first phase is 58 duplex buildings with 116 homes.
What was reported
- Lakewood's planning board approved splitting land at 688 and 752 Cross Street and 2 Augusta Boulevard into 129 lots for The Parke at Lakewood
- This first phase is 58 duplex buildings, 116 homes. The developer said it needs no exceptions to the zoning rules
- Later phases were shown for reference only and will come back to the board as their own applications
The story
On September 1, Lakewood Township's planning board voted all in favor to approve 129 new lots for The Parke at Lakewood, LLC, on land at 688 and 752 Cross Street and 2 Augusta Boulevard.
This vote covers the first phase of a larger plan for the whole site that the board approved earlier. The developer's attorney said this phase is 58 duplex buildings, 116 homes, fits the town's zoning rules, and already has the state's coastal permit (CAFRA). The developer's engineer said phases 2 through 5 were shown only for reference and are not part of this approval.
The minutes describe the layout: public roads 32 feet wide, 141 on-street parking spaces, and a community building and a playground in each phase. The engineer described a 41-acre buffer. The Cross Street road work from the earlier approval has to be finished before the final move-in approval for phase 1, and the engineer said those three lanes are already built.
Board members disagreed about how many homes the earlier plan allows across all phases, and said they would take that up when later phases are applied for.
South Jersey New Construction works with buyers, builders and land owners across Ocean County. If you are weighing new construction near Cross Street, or own land in Lakewood, we are glad to talk it through.
Written by Justin Kelly, NJ Real Estate Broker-Salesperson, from the Lakewood Township Planning Board minutes for September 1, 2026.
What to know
Phase 1 is 116 duplex homes on public roads, and the plan puts a community building and a playground in each phase. If you are buying new construction or own land in Ocean County, we work with buyers, builders and land owners there.