1. Filed
  2. Hearing held
  3. Approved
  4. State permits pending
  5. Under construction
  6. Fully built

No new board documents in about 90 days. The stage shown is the last step it reached.

Stage
Hearing held, no final approval yet
Town
Upper Deerfield Township
County
Cumberland County
Type
Commercial
Latest step
Aug 11, 2025

The project

Three warehouse buildings totaling 1,710,500 sq ft and a new Commerce Drive (Big Oak Road Extension) on 125.15 acres in the Highway 77 Redevelopment Area.

Where it is

The exact site has not been made public, so it is shown at the middle of Upper Deerfield Township.

Steps so far

  1. Hearing held

    The Upper Deerfield Township Planning Board memorialized Resolution 6-2025 granting preliminary major site plan approval with design waivers.

    Source: Upper Deerfield Township Planning Board · Read the document
Back to the development map

Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.