- Filed
- Hearing held
- Approved
- State permits pending
- Under construction
- Fully built
No new board documents in about 90 days. The stage shown is the last step it reached.
- Stage
- Hearing held, no final approval yet
- Town
- Pennsville Township
- County
- Salem County
- Type
- Commercial
- Latest step
- Jun 22, 2026
The project
Ordinance A-13-2026 defines data centers and computer centers and prohibits them in all zoning districts.
Where it is
The exact site has not been made public, so it is shown at the middle of Pennsville Township.
Steps so far
- Hearing held
The Pennsville Township Combined Planning/Zoning Board reviewed Ordinance A-13-2026 for Master Plan consistency and voted to send its decision to the Township Committee as Resolution 26-13.
Source: Pennsville Township Combined Planning/Zoning Board · Read the document - Hearing held
The board memorialized Resolution 26-13 finding Ordinance A-13-2026 not inconsistent with the Master Plan, with a recommendation to consider data centers as a conditional use in specific districts.
Source: Pennsville Township Combined Planning/Zoning Board · Read the document
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.