1. Filed
  2. Hearing held
  3. Approved
  4. State permits pending
  5. Under construction
  6. Buyers moving in
  7. Fully built

No new board documents in about 90 days. The stage shown is the last step it reached.

Stage
Hearing held, no final approval yet
Town
Jackson Township
Type
Residential
Size
13 homes
Latest step
Apr 15, 2026

The project

A proposal to drop an approved religious school and put 13 single-family houses on the same 17-acre Cassville Road tract instead, on a new street, at a density the zone does not allow.

Where it is

Steps so far

  1. Hearing held

    The board took testimony on the use variance and carried the application to July 15, 2026 on a unanimous motion. The board engineer raised an expired letter of interpretation and the applicant was not ready to produce an updated environmental impact statement; neighbours asked about the water table, traffic and what happens to the approved school.

    Source: Jackson Township Zoning Board of Adjustment · Read the document
Back to the development map

Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.