- Stage
- Hearing held, no final approval yet
- Town
- Egg Harbor Township
- County
- Atlantic County
- Type
- Residential
- Latest step
- Jan 9, 2026
The project
An amended Timber Ridge Redevelopment Plan for a 48-acre site that replaces planned garden apartments with 215 townhouses at up to 4.75 units an acre, ten of them affordable.
Where it is
The exact site has not been made public, so it is shown at the middle of Egg Harbor Township.
Steps so far
- Hearing held
Pinelands Commission packet lists Egg Harbor Township Ordinance 33-2025, adopting the amended Timber Ridge Redevelopment Plan, among ordinances not requiring Commission action.
Source: New Jersey Pinelands Commission · Read the document - Hearing held
Pinelands Commission minutes record staff's note that the amended Timber Ridge plan swaps multi-family units for townhouses without changing density or credits required.
Source: New Jersey Pinelands Commission · Read the document
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.