- Stage
- Approved, not yet underway
- Town
- East Greenwich Township
- County
- Gloucester County
- Type
- Commercial
- Size
- 700,000 sq ft
- Latest step
- Dec 9, 2021
The project
A 700,000 square foot warehouse distribution centre on the north-east side of Democrat Road, about 1,650 feet south of Swedesboro Avenue: 679,000 square feet of warehouse and 21,000 square feet of office, with 146 truck parking spaces and 400 passenger vehicle spaces. The board granted preliminary and final major site plan approval together with bulk and parking variances.
Steps so far
- Approved
The Combined Planning/Zoning Board deemed application 2020-10 complete, took no public comment, and granted preliminary and final major site plan approval together with bulk and parking variance approval, 9-0.
Source: East Greenwich Township Combined Planning/Zoning Board · Read the document - Approved
The board adopted Resolution 2021-16, an administrative approval for Knight Owl Holdings V, LLC, by unanimous roll call.
Source: East Greenwich Township Combined Planning/Zoning Board · Read the document
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.